MBR Solar Park Phase 6 - a Solar Independent Power Producer in UAE. Capacity 1.8 GW. Winning consortium: Masdar. LCOE: USD $0.0162/kWh. Status: Construction.
Country
UAE
Procurer
DEWA
City / region
Saih Al-Dahal, Dubai
Capacity
1.8 GW
Status
Construction
LCOE
USD $0.0162/kWh
Winning consortium
Masdar - equity: DEWA 60% / Masdar 40%
Procurement timeline
RFQ: Jun 2022
RFP: Dec 2022
Bid submission: Jul 2023
Preferred bidder: Aug 2023
Commercial close: Q4 2023
Financial close: Feb 2024
PCOD: 2026
Prequalified bidders
23 PQ · 2 final bids
Masdar
ACWA Power
EDF
Marubeni
TotalEnergies
JinkoPower
Engie
Sembcorp
Runner-up bidders & tariffs
ACWA Power
Financing
Capex: USD 1.5 bn
Debt: USD 1.2 bn
Lenders: StanChart, SocGen, MUFG, Mizuho, SMBC, CACIB, Natixis, FAB
Tenor: 29-yr soft mini-perm
Technical scope
Process: Bifacial + trackers
Lowest LCOE in MBR park history. First MBR phase single-sponsor
Notes
23 EOI; 2 priced bids.
EPC contractor: China Energy Engineering / PowerChina