MBR Solar Park Phase 2
MBR Solar Park Phase 2 - a Solar Independent Power Producer in UAE. Capacity 200 MW. Winning consortium: ACWA Power + TSK. LCOE: USD $0.0584/kWh. Status: Operational.
Country UAE
Procurer DEWA
City / region Saih Al-Dahal, Dubai
Capacity 200 MW
Status Operational
LCOE USD $0.0584/kWh
Winning consortium ACWA Power + TSK - equity: DEWA 51% / ACWA 41.65% / TSK 7.35%
Procurement timeline
RFP: 2014Bid submission: 20 Nov 2014Preferred bidder: Jan 2015Commercial close: 2015Financial close: 2015PCOD: Mar 2017
Prequalified bidders 24 PQ · 10 final bids
ACWA + TSK First Solar Masdar consortium Marubeni FRV Sky Solar SunEdison 6 more
Runner-up bidders & tariffs First Solar (2nd) - USD $0.0698/kWh
Financing Capex: USD 330 MDebt: USD 245 MLenders: FAB (FGB+NBAD), UNB, Standard CharteredTenor: ~24-yr mini-perm
Technical scope Process: CdTe thin-film, fixed tilt
Global-record tariff at 2014 bid - 20% below previous
Notes Shuaa Energy 1 SPV. First MBR Solar Park IPP.
EPC contractor: TSK (CdTe thin-film, 2.3M modules)