Al Sadawi (2 GW) PV

Al Sadawi (2 GW) PV - a Solar Independent Power Producer in Saudi Arabia. Capacity 2.0 GW. Winning consortium: Masdar + GD Power + KEPCO. LCOE: USD $0.0129/kWh. Status: Financial close.

Solar IPP reference plant
Country
Saudi Arabia
Procurer
SPPC
City / region
Eastern Province (Al Sadawi)
Capacity
2.0 GW
Status
Financial close
LCOE
USD $0.0129/kWh

Winning consortium

Masdar + GD Power + KEPCO

Procurement timeline

Prequalified bidders

23 PQ · 3 final bids

Financing

Technical scope

Process: Bifacial mono-PERC + trackers

Largest R5 award; LCOE 1.29c world-record at award

Notes

R5 flagship; PPA 19 Nov 2024.

EPC contractor: PowerChina

Sources

Open the full Solar IPP benchmark →