Duqm Power Plant CCGT - a Independent Water & Power Project in Oman. Capacity 877 MW. Winning consortium: KOWEPO + EWEC + Nebras + Bahwan. Status: Awarded 22 Jan 2026.
KOWEPO + EWEC + Nebras + Bahwan - equity: KOWEPO 35% / Nebras 30% / EWEC 30% / Bahwan 5%
Process: CCGT (CCUS-ready)
First major KOWEPO IPP in GCC
EPC contractor: TBD (~USD 898M)
Part of the GulfInfra · GCC Infrastructure Library - a free open-source benchmark of 136 public-private partnership procurements across the GCC. Methodology: how we build this.