Barka 2 IWPP (SMN Barka)

Barka 2 IWPP (SMN Barka) - a Independent Water & Power Project in Oman. Capacity 678 MW. Winning consortium: Mubadala + Suez + Multitech. Status: Operational.

IWPP / IPP reference plant
Country
Oman
Procurer
OPWP
City / region
Barka
Capacity
678 MW
Status
Operational
Power tariff
Not publicly disclosed

Winning consortium

Mubadala + Suez + Multitech - equity: SMN Barka SPV

Procurement timeline

Financing

Technical scope

Process: CCGT + SWRO

Includes Al Rusail brownfield acquisition

EPC contractor: Doosan / Sidem

Sources

Open the full IWPP / IPP benchmark →

Part of the GulfInfra · GCC Infrastructure Library - a free open-source benchmark of 136 public-private partnership procurements across the GCC. Methodology: how we build this.